3 lighting points for the kitchen( Stove, sink and wash area )
Supporting frame for mounting of false ceiling
Week 6 saw the fabrication and completion of the false ceiling and lightbox for the hall and foyer of the main bedroom entrance.
We also asked the ID to fit in curtain pulmets into the false ceiling for the hall curtains and master bedroom so that the rails for the day and night curtains are hidden from view. We also made pulmet in front of the main door entrance(see above) to hide the rail for the string curtains which we are putting up to give some privacy to the living room.
Our ID also fabricated and installed a false wall backing which the walk in wardrobe will be built into. The wall will also serve to partition the study area from the walk in wardrobe.
We will be mounting an IKEA Full height mirror at the side of the wall. We took the dimensions of the mirror and got our ID to build the sidewall to the mirror dimensions so that it will be a good fitting.
WEEK 7
LAMINATED FLOORING LAID
Master Bedroom Laminated Flooring from Supreme
This week, the contractor laid the laminated flooring from SUPREME. This brand was recommended by our ID due to it' s combination of higher quality and 'dont breaqk the bank prices'. We chose a dark shade of brownish black grain to blend in with our rooms' grey, black , red , cozy concept. The workmanship is quite good especially in the skirtings and most importantly, the flooring was level and there were no hollow sounds when walking on it.
Common Room Laminated Flooring
ELECTRICAL WORKS PT 2
The electrician also came up to complete the cabling of the electrical wires. We were surprised that he installed a "branded'' Miniature Circuit Breaker (MCB)Box - HAGER brand from France ( See Below picture) . We know about this brand because we bought a HAGER Contactor Unit ( Used to link two separate switches to one storage heater)for our storage heater, which was recommended by the electrical shop where we bought our LEGRAND switches. In preparation for the painting of the house, our contractor gave a first wash up of the house which finally meant we could step into the house without our shoes and also to see the flooring as one whole complete uncovered layer.
Finally , Shiny homogeneous flooring of the Hall ( Above and Below pictures ) !
Our cleaned kitchen , common toilet and master toilet! Sparkling !
PAINTING
Mid-week, the painters came to our house and brought some colours to our house. We chose primary colours of two shades of grey and one shade of white with two fun colours of red and orange. Pictures tell a thousand words so view the pictures :
Living Room
Living Room colours - Nippon 5069 Galaxy(darker Grey) and ICI Dolphin 20278(Light Grey)
Dining Area Wall Colour - Nippon 5069 Galaxy ( Dark Grey )
Master Bedroom
(Above) Master Bedroom Colour - ICI 20278 Dolphin
(Above and below) Walk In Wardrobe - ICI 20278 Dolphin
Passage to Study Area and Walk In Wardrobe
(Above) Wall Colour :Nippon 5046 Spectrum Red
Common Bedroom ( The Fun Room )
(Above) Common Rm Colour : ICI SP27801 Fiesta Orange
Master Toilet
Common Toilet
Kitchen
Store Room
INSTALLATION OF CARPENTRY WORKS ( PART I )
The first installment of the carpentry works began today on the last weekday of Week 7. The contractor put up the first sections of the kitchen cabinet and the complete walk in wardrobe. The hob and kitchen sink were also laid in before the second stage of mounting the solid top of the kitchen cabinet.
( Above ) L -shaped Black Glossy Laminated Kitchen Cabinet ( 38ft)
Sink and hob adjacent with workspace for two persons to be simultaneously working in kitchen together. ( Above )
( Above )Unfinished Wooden backing for dish rack and shelving cum sink section
Our half installed Rinnai RB2C-G Inner Burner Hob
( Above ) Insertion of the BLANCO kitchen sink ( Anthracite Grey colour)
( Above ) 1st section of Walk In Wardrobe with glossy grey laminate
( Below ) 2nd section of the Walk in Wardrobe ( Below ) We constructed a pulmet for installation of a suede curtain in place of doors ( to reduce cost ) to reduce dust retention and for privacy.
NEXT : WEEK 8 - ELECTRICAL WORKS ? PLUMBING ? CARPENTRY PART 2